Dear Resident/Business Owner,
The City’s contractor for the W. State Street intersection improvements project will begin work as outlined below, weather permitting.
- July 7 -8: Asphalt milling of the intersections
- July 13 -14: Placement of the fibermat layer
- July 16 -17: Asphalt resurfacing (Night operations from 6 pm to 6 am)
W.State is our busiest roadway in the City and traffic maintenance will be a challenge. There will be detours in place to route traffic around the work zones, however it is intended to keep one lane of traffic open in each direction when the contractor is working.
Please see the maps below of the proposed work.
The City understands the inconvenience and appreciates your cooperation and patience. If you have any questions or concerns, please call the Engineer’s Office at 419-334-8963 or the Administration Office at 419-334-5900.